Central Nuclear de Trillo - Trillo, Guadalajara, España
Posted by: Groundspeak Premium Member xeocach
N 40° 41.787 W 002° 37.275
30T E 531999 N 4505130
En funcionamiento desde 1988 // In operation since 1988
Waymark Code: WM19FR9
Location: Castilla-La Mancha, Spain
Date Posted: 02/19/2024
Published By:Groundspeak Charter Member GeoBlank
Views: 0

[ES] “Es la última central nuclear en entrar en funcionamiento en España, su acoplamiento a la red eléctrica se dio el 23 de mayo de 1988 y el inicio de la operación comercial el 6 de agosto de 1988. El 22 de abril de 2013 se alcanzaron los 200 TWh de producción acumulada.

La central nuclear de Trillo fue concebida como una central de base, es decir, de funcionamiento ininterrumpido y alto grado de disponibilidad. En condiciones normales de operación, alcanza una producción del orden de 8.000 GWh/año. Esta energía representa un 40 % de la potencia hidráulica instalada en 34 centrales hidroeléctricas en la cuenca del río Tajo. Trillo consigue una utilización del 80 % de su potencia, frente al 30 % del parque hidráulico del Tajo.

El reactor nuclear de Trillo, un reactor de agua a presión (PWR) con una potencia instalada de 1067 MWe, pertenece a la denominada tercera generación de centrales nucleares españolas.

Esta central utiliza cada año una media de 80 toneladas de óxido de uranio enriquecido con uranio-235 para llevar a cabo la producción eléctrica. Durante el año 2020 la producción neta de la central nuclear de Trillo fue de 7.729,61 millones de kWh y la producción bruta fue de 8275,82 millones de kWh. Estos datos suponen el 15% de la producción nuclear española y el 3% de la producción eléctrica nacional.”

(Fuente)


[EN] “It is the last nuclear power plant to come into operation in Spain, its connection to the electrical grid occurred on May 23, 1988 and the beginning of commercial operation on August 6, 1988. On April 22, 2013, 200 TWh of accumulated production was reached.

The Trillo nuclear power plant was conceived as a base plant, that is, with uninterrupted operation and a high degree of availability. Under normal operating conditions, it reaches a production of around 8,000 GWh/year. This energy represents 40% of the hydraulic power installed in 34 hydroelectric plants in the Tagus River basin. Trillo achieves a utilization of 80% of its power, compared to 30% for the Tajo hydraulic park.

The Trillo nuclear reactor, a pressurized water reactor (PWR) with an installed power of 1067 MWe, belongs to the so-called third generation of Spanish nuclear power plants.

This plant uses an average of 80 tons of uranium oxide enriched with uranium-235 each year to carry out electricity production. During 2020, the net production of the Trillo nuclear power plant was 7,729.61 million kWh and the gross production was 8,275.82 million kWh. These data represent 15% of Spanish nuclear production and 3% of national electricity production.”

(Source)

Operational: Yes

Visitor Center: Yes

Year Built: 05/23/1988

Web Address: [Web Link]

Year Retired: Not listed

Search for...
Geocaching.com Google Map
Google Maps
MapQuest
Bing Maps
Nearest Waymarks
Nearest Nuclear Power Plants
Nearest Geocaches
Create a scavenger hunt using this waymark as the center point
Recent Visits/Logs:
There are no logs for this waymark yet.